Hello,
I want to track homeworking, independantly from activities performed.
It sounds that "Planned intervention" feature with 'Intervention Modality" can be used for that.
However it's impossible to set an intervention modality if available workload for a ressource is null. (imputation on activities already done for this day).
I got an error message "unsufficiant workload for this ressource".
Am i using the feature the right way ?
Thanks
Br
No, it's right.
Defaut behavior block entering Planned Intervention (that books planned work or real work) that would additionnaly to existing real work be more than resource capacity.
But you can change this behavior with parameter on Global Parameter > Planning > effect of capacity on planned interventions : select none...
Thanks you !
Br