Intervention modality can not be setted after imputation is done ?

3 Posts
2 Users
0 Reactions
1,925 Views
(@milien56)
Posts: 26
Active Member
Topic starter
 
[#8113]

Hello,

I want to track homeworking, independantly from activities performed.
It sounds that "Planned intervention" feature with 'Intervention Modality" can be used for that.
However it's impossible to set an intervention modality if available workload for a ressource is null. (imputation on activities already done for this day).
I got an error message "unsufficiant workload for this ressource".
Am i using the feature the right way ?

Thanks
Br


 
Posted : 02 Mar 2022 19H46
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

No, it's right.
Defaut behavior block entering Planned Intervention (that books planned work or real work) that would additionnaly to existing real work be more than resource capacity.
But you can change this behavior with parameter on Global Parameter > Planning > effect of capacity on planned interventions : select none...


 
Posted : 03 Mar 2022 2H06