Hello,
Is it planned to implement Kanban per project. As I see (perhaps i am wrong), we can define multiple Kanban but not per project. Is is good to manage a portfolio but if for example, we want to manage multiple differents columns projets per projects, it is not possible.
Best regards,
Hi,
It is a planned evolution (ticket #673).
Not planned on a version yet.
We estimated the cost for a client that could sponsor this evolution, but finaly he did not validate the quote.
So evolution is still in low priority.
Hi,
Thank you for your answer. If it is not planned currently to create Kanban for individual project, is it planned to offer the possibility (add to the selector list)to select project as the same as ticket, activity, actions, requirements.
Regards,
Yes, it already works this way.
Selection in the project selector is applied to Kanban items.
You can alos define as many Kanban boards as you want, so you can define a Kanban for each layout you want.
Only things you cannot do :
- have a Kanban of projets (items are projetcs) - This is subject of ticket #673
- automatically apply a Kanban when you select a projet (subject of your initial request)
Hi,
Thank you for your answer. I will check the possibilities offered.