I've copied a project with these activities and programming (dates). Is it possible to move all dates (of activities, milestones ..) automatically, just by moving the dates of the PROJECT?


 
Posté : 23 Sep PM 13:099
(@babynus)
Posts: 14952
Membre Admin
 

No, not possible for "requested" and "validated" dates.
For planned date : a new planning calculation should do the job.


 