No update % with imputation

4 Posts
2 Utilisateurs
0 Reactions
2,607 Vu
(@belsebou72)
Posts: 9
Active Member
Début du sujet
 
[#3757]

HI,
I don't want my progress data activities move with time imputation.
it is possible


 
Posté : 17 Oct PM 12:1010
(@babynus)
Posts: 14952
Membre Admin
 

No,

With what do you want to move progress ?


 
Posté : 17 Oct PM 12:1010
(@belsebou72)
Posts: 9
Active Member
Début du sujet
 

Hi,
I would like
each resources enter their time spent
each resources enter progress data as a projet for example

do the planning mode "fixed term" allow this mehod ?
Best regards


 
Posté : 17 Oct PM 13:1010
(@babynus)
Posts: 14952
Membre Admin
 

No, ProjeQtOr is effort driven.
It is mandatory for capacity planning.
So progress is automatically calculated from real work, whatever the planning mode.


 
Posté : 17 Oct PM 18:1010