No update % with imputation

4 Posts
2 Users
0 Reactions
2,650 Views
(@belsebou72)
Posts: 9
Active Member
Topic starter
 
[#3757]

HI,
I don't want my progress data activities move with time imputation.
it is possible


 
Posted : 17 Oct 2016 12H28
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

No,

With what do you want to move progress ?


 
Posted : 17 Oct 2016 12H42
(@belsebou72)
Posts: 9
Active Member
Topic starter
 

Hi,
I would like
each resources enter their time spent
each resources enter progress data as a projet for example

do the planning mode "fixed term" allow this mehod ?
Best regards


 
Posted : 17 Oct 2016 13H17
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

No, ProjeQtOr is effort driven.
It is mandatory for capacity planning.
So progress is automatically calculated from real work, whatever the planning mode.


 
Posted : 17 Oct 2016 18H31