HI,
I don't want my progress data activities move with time imputation.
it is possible
Posted : 17 Oct 2016 12H28
No,
With what do you want to move progress ?
Posted : 17 Oct 2016 12H42
No, ProjeQtOr is effort driven.
It is mandatory for capacity planning.
So progress is automatically calculated from real work, whatever the planning mode.