Hello,
I currently test the use of ProjeQtOr. It's possible to create a link with a delay.
But when I want to overlap 2 activities: it seems it's not possible that a negative delay is taken into account ?
Regards,
JP
HI,
Overlapping is possible by specifying a negative number. However, this does not mean that planification will necessarily take this into account, First of all, calculation depends on ongoing priorities and availabilities of resources.
Regards
Thanks for you answer.
It works! Probably , I have forgotten to tick the automatic update of the Gantt 😉
Regards,
Jp
Perfect. Indeed after making changes, the automatic calculation is done automatically only if the user is on the planning screen and the box is checked. Otherwise from another screen even if the box is checked, you have to manually restart the calculation by clicking on the main button after coming back to this planning screen. This protects against inappropriate recalculations.
Alainforma.