Hi all,
I tested version 3.01 and I have put together a display problem Gant charts. If I do not select a project by project it is impossible to visualize the overall schedule. Configuration variable to the maximum number is set to 30 and I must have 25 activities on projects that are not displayed. I did the test by emptying the cache on both browsers.
The icon turns waiting a very long time (30s) then the page is empty:
The page works projects with 10 activities.
I hope that this problem will be solved, because I unfortunately went into production with version 3.00 🙁 that it works at display Gant with many more projects.
Thank you for your help, if you need more info do not hesitate.
Could you check if on of your projects or activities name has a " (double quote) ?
If yes : try and replace it with ' (single quote).
If it fixes issue, then it is a bug that is fixed on V3.0.2.
Thank you for the correction.
Strongly that the version 3.0.2 so it seems to fix a lot of small problems 🙂 .
Thank you.