Hello,
I have a periodic meeting called "REUNION BE - LUNDI".
This meeting takes place every week on Monday (9H30 - 11H00).
On planning view, I have one line per Monday meeting (even for a meeting that has already taken place). So we have a lot of lines that are displayed
Instead of one line per meeting, is there a possibility to have one line displayed for all the meeting dates (from start date to end date) ?
If this is not possible, for previous meeting, is there a possibility to hide meetings that have already taken place ?
Best Regards,
