Hi,
I have a little problem with the task and dependency calculation. I'll add the screenshot. it might help you to understand what I mean.
My problem is that the starting date is always the planning date and not the real flow. and it,s not possible to modify the planned date.
How can i make my project calculate the starting date of every task with the end of the predecessor.
Thanks
Benoit
Benoit
Define some work on each activity (add assignement with assigned work) or set planning mode to "fix duration".
Then run planning calculation.