Planning project dependency calculation

2 Posts
2 Users
0 Reactions
3,988 Views
(@benoit-s)
Posts: 4
Active Member
Topic starter
 
[#3451]

Hi,
I have a little problem with the task and dependency calculation. I'll add the screenshot. it might help you to understand what I mean.
My problem is that the starting date is always the planning date and not the real flow. and it,s not possible to modify the planned date.
How can i make my project calculate the starting date of every task with the end of the predecessor.

Thanks

Benoit


Benoit

 
Posted : 09 Jun 2016 5H06
(@babynus)
Posts: 14952
Member Admin
 

Define some work on each activity (add assignement with assigned work) or set planning mode to "fix duration".
Then run planning calculation.


 
Posted : 09 Jun 2016 10H45