[#5658]

Hi,

I have a pool of ressource (two people) assigned to a task, but these two people can't fill their timesheet for the same day for this task. Each time one of this two fill his own, it delete the one of the other. Is that normal? Is their an other way to process?

The idea is to be able to fill the remaining work of the task directly for the pool of ressource and not for each ressource.

Thanks

Guillaume G, Portalliance.


 
Posté : 4 Jan PM 17:011
(@babynus)
Posts: 14952
Membre Admin
 

This is an issue fixed on V7.3.2


 
Posté : 7 Jan PM 23:011