Hi,
I have a pool of ressource (two people) assigned to a task, but these two people can't fill their timesheet for the same day for this task. Each time one of this two fill his own, it delete the one of the other. Is that normal? Is their an other way to process?
The idea is to be able to fill the remaining work of the task directly for the pool of ressource and not for each ressource.
Thanks
Guillaume G, Portalliance.
Posté : 04/01/2019 5:17 pm
This is an issue fixed on V7.3.2
Posté : 07/01/2019 11:42 pm