Real work allocation

5 Posts
3 Utilisateurs
0 Reactions
2,277 Vu
(@bion)
Posts: 70
Active Member
Début du sujet
 
[#5203]

Hello,
I wanted to know if there's a way on the real work allocation screen to filtrer or to display only a specific project and not all the projects where the resource is asign.

thanks .


 
Posté : 30 Mai PM 15:055
(@alain-fourastie)
Posts: 366
Membre Moderator
 

Hello,
It is impossible, you can just hide project(s) for which none real work are imputated


 
Posté : 30 Mai PM 16:055
(@bion)
Posts: 70
Active Member
Début du sujet
 

I've got another question about real work allocation, is there a way to clear ever real work enter by every ressource in order to delete some projects ?


 
Posté : 4 Juin PM 12:066
(@alain-fourastie)
Posts: 366
Membre Moderator
 

Hi,
You can modify through the application each resource and its work, one by one, on a project provided you have the rights to do it.
Also, you can go directly to the database to clean, in one click, the desired data.


 
Posté : 4 Juin PM 13:066
(@babynus)
Posts: 14952
Membre Admin
 

Also, you can go directly to the database to clean, in one click, the desired data.

NO !!!!!
NEVER DO THAT !!!!

What you can do is usee API to delete work data, but never directly update the database.


 