Forum

Notifications
Retirer tout

Baseline

3 Posts
3 Utilisateurs
0 Reactions
2,614 Vu
(@bion)
Posts: 70
Estimable Member
Début du sujet
 
[#5204]

Hello,
I found out that we can save a baseline for a planning and superimpose it with the actual planning.
My probleme is i can't figure out how it work and i can't display the saved baseline on my planning. Am i doing something wrong ?

thanks for helping


 
Posté : 31/05/2018 1:17 pm
Gautier
(@gautier)
Posts: 207
Membre Admin Registered
 

Hello,

To save a baseline click on button " save a baseline of planning " then select one project and name your baseline.
Once saved select your baseline under " show baseline " on buttom or on top. ( Be careful of you current selected project, it has to correspond to your baseline project )


 
Posté : 31/05/2018 1:38 pm
(@narayanaras)
Posts: 150
Reputable Member
 

The Planning screen has these buttons to save a baseline and to display saved baselines.

You can compare your current planning against TWO baselines simultaneously.
The Gantt chart shows three sets of bars simultaneously.
One of them appears above the current planning bars, and the other appears below the current planning bars.

If you planning has changed by a wide margin, you may have to pan across the Gantt chart to find your baseline!


 
Posté : 01/06/2018 1:29 pm
Share:
Retour en haut