real work allocation empty

9 Posts
2 Users
0 Reactions
6,109 Views
(@sergio)
Posts: 6
Active Member
Topic starter
 
[#4010]

Hello,

What is the most likely reason why I have no element in real work allocation even if I have a valid task that appears in te ressource planning.


 
Posted : 15 Jan 2017 12H44
(@babynus)
Posts: 14952
Member Admin
 

Possibly your project is still "under construction"


 
Posted : 15 Jan 2017 13H06
(@sergio)
Posts: 6
Active Member
Topic starter
 

No I have verified and the flag is at 0 in the DB (Its obious that it is my first project on ProjeQtOr)


 
Posted : 15 Jan 2017 13H13
(@babynus)
Posts: 14952
Member Admin
 

So you just did not define assignment to a resource for the activity.


 
Posted : 15 Jan 2017 13H30
(@sergio)
Posts: 6
Active Member
Topic starter
 

I have myself defined as ressource with assigned days for two activities that appears in the ressources planning. I think that the assignment is materialized with a brighter green color for the activity in the planning.


 
Posted : 15 Jan 2017 15H16
(@babynus)
Posts: 14952
Member Admin
 

Yes,
Since V6.0 activities without assigned work appear in a lighter (more pale) color.


 
Posted : 15 Jan 2017 15H21
(@sergio)
Posts: 6
Active Member
Topic starter
 

Why can't i see any activity to report in real work.


 
Posted : 15 Jan 2017 15H28
(@babynus)
Posts: 14952
Member Admin
 

Cannot analyse with so little information.
Please post print screen for :
- Project detail
- Activity detail
- Real Work Allocation


 
Posted : 15 Jan 2017 15H39
(@sergio)
Posts: 6
Active Member
Topic starter
 

When making the screenshot I discovered my error: I didn't remember that I've set the project as template. I was sure from the beginning it was a silly detail. Sorry for disturbance. Anyway I think I will continue with ProjectQtOr which seems to be very complete. I'll confirm my opinion when having practiced with it.

Thanks!


 
Posted : 16 Jan 2017 6H50