Hello,
What is the most likely reason why I have no element in real work allocation even if I have a valid task that appears in te ressource planning.
Possibly your project is still "under construction"
No I have verified and the flag is at 0 in the DB (Its obious that it is my first project on ProjeQtOr)
So you just did not define assignment to a resource for the activity.
I have myself defined as ressource with assigned days for two activities that appears in the ressources planning. I think that the assignment is materialized with a brighter green color for the activity in the planning.
Yes,
Since V6.0 activities without assigned work appear in a lighter (more pale) color.
Why can't i see any activity to report in real work.
Cannot analyse with so little information.
Please post print screen for :
- Project detail
- Activity detail
- Real Work Allocation
When making the screenshot I discovered my error: I didn't remember that I've set the project as template. I was sure from the beginning it was a silly detail. Sorry for disturbance. Anyway I think I will continue with ProjectQtOr which seems to be very complete. I'll confirm my opinion when having practiced with it.
Thanks!