Real work Allocation : Nothing appaears

4 Posts
3 Utilisateurs
0 Reactions
2,800 Vu
(@rgrezes)
Posts: 2
New Member
Début du sujet
 
[#3767]

I'm project manager , I created and planned some activities , but the screen RWA is empty!
See attached print screen


 
Posté : 20 Oct PM 12:1010
(@babynus)
Posts: 14952
Membre Admin
 

Possibly indicator "under construction" is checked on your projects.
You may not enter real work for projects that are still "under constrcution".


 
Posté : 20 Oct PM 14:1010
(@rgrezes)
Posts: 2
New Member
Début du sujet
 

The project status was not 'in progress'
After moving it to'in progress' I can assign time in RWA


 
Posté : 20 Oct PM 18:1010
(@richard-pare)
Posts: 165
Active Member
 

The problem was your project was under construction.

When you have changed its status to 'in progress', automatically the project can no longer be under construction.


 
Posté : 20 Oct PM 18:1010