Real work Allocation : Nothing appaears

4 Posts
3 Users
0 Reactions
2,821 Views
(@rgrezes)
Posts: 2
New Member
Topic starter
 
[#3767]

I'm project manager , I created and planned some activities , but the screen RWA is empty!
See attached print screen


 
Posted : 20 Oct 2016 12H35
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

Possibly indicator "under construction" is checked on your projects.
You may not enter real work for projects that are still "under constrcution".


 
Posted : 20 Oct 2016 14H30
(@rgrezes)
Posts: 2
New Member
Topic starter
 

The project status was not 'in progress'
After moving it to'in progress' I can assign time in RWA


 
Posted : 20 Oct 2016 18H08
(@richard-pare)
Posts: 165
Active Member
 

The problem was your project was under construction.

When you have changed its status to 'in progress', automatically the project can no longer be under construction.


 