Hello
What's reassessed work ? and how it's calculed
Some times when i calcule planning for an activitity witch valitdated for example on 21/10/2015 to 21/810/2015 (1 day), the system calculate others planned dates , for example form 22/10/2015 to 02/11/2015 !!
PS: my planning parameter is :" Fixed duration"
Can i entry manually a planned date ?
Thanks !
What's reassessed work ? and how it's calculed
Reassessed = real + left,
it is re-evaluated work from real input and re-evaluation of left work.
Some times when i calcule planning for an activitity witch valitdated for example on 21/10/2015 to 21/810/2015 (1 day), the system calculate others planned dates , for example form 22/10/2015 to 02/11/2015 !!
If you enter some work, left work is planned depending on resource avalability.
PS: my planning parameter is :" Fixed duration"
If you choose "fixed duration", you should not define work (no assignment), otherwise, task is planned "regulliarly" for the duration.
Can i entry manually a planned date ?
No, because they are planned : you don't plan. ProjeQtOr does.