reassessed & planned work

2 Posts
2 Users
0 Reactions
3,273 Views
(@tanabene)
Posts: 2
Active Member
Topic starter
 
[#2668]

Hello

What's reassessed work ? and how it's calculed
Some times when i calcule planning for an activitity witch valitdated for example on 21/10/2015 to 21/810/2015 (1 day), the system calculate others planned dates , for example form 22/10/2015 to 02/11/2015 !!
PS: my planning parameter is :" Fixed duration"

Can i entry manually a planned date ?

Thanks !


 
Posted : 23 Oct 2015 18H48
(@babynus)
Posts: 14952
Member Admin
 

What's reassessed work ? and how it's calculed

Reassessed = real + left,
it is re-evaluated work from real input and re-evaluation of left work.

Some times when i calcule planning for an activitity witch valitdated for example on 21/10/2015 to 21/810/2015 (1 day), the system calculate others planned dates , for example form 22/10/2015 to 02/11/2015 !!

If you enter some work, left work is planned depending on resource avalability.

PS: my planning parameter is :" Fixed duration"

If you choose "fixed duration", you should not define work (no assignment), otherwise, task is planned "regulliarly" for the duration.

Can i entry manually a planned date ?

No, because they are planned : you don't plan. ProjeQtOr does.


 
Posted : 23 Oct 2015 20H44