[#246]

In Activity - New Task if I try to add resource using "+" in assignment area it will not populate the list of resources and manual typing producing always "The value entered is not valid" message.
I can add resource using "responsible" field (still no population for drop down box but search button is producing resource list) but only ONE resource. Looking like there is no way to add second resource. So, what I am doing wrong?


 
Posted : 22 Nov 2011 14H08
(@babynus)
Posts: 14952
Member Admin
 

Hi,

Resource must be affected to the project.
Then resource appears in the list and can be assigned to the activity.

Regards.


 
Posted : 22 Nov 2011 15H25
Evgueni Kolossov
(@ekolossov)
Posts: 566
Contributor
Topic starter
 

It is there already!


 
Posted : 22 Nov 2011 15H27
(@babynus)
Posts: 14952
Member Admin
 

???


 
Posted : 22 Nov 2011 16H34
Evgueni Kolossov
(@ekolossov)
Posts: 566
Contributor
Topic starter
 

Sorry - found the reason for the problem - it is in affectations which done wrong. Can you please explain how to do affectations for multiple projects when people involved kind of time-to-time in different projects but on 100%?
Regards


 
Posted : 22 Nov 2011 16H37
(@babynus)
Posts: 14952
Member Admin
 

Affectation definition includes affectation rate to the project.
For instance, if a resource works evenly on 5 project, oyu can define affectation rate at 20% on each.
This way, planning process will plan work for resource 1 day per project each week.

Another way is to assign to tasks at a 20% rate. Then resource will be planned only 20% on each project each day.


 
Posted : 22 Nov 2011 18H15
Evgueni Kolossov
(@ekolossov)
Posts: 566
Contributor
Topic starter
 

Thank you for your answer but I still cannot figure out how to do that if I have person who is working say 1 week 100% on 1 project and another week 100% on another project?
Regards


 
Posted : 22 Nov 2011 18H38
(@babynus)
Posts: 14952
Member Admin
 

Just define resources at 100% on each project and activities.
Then play with priorities of activities (lower number is planned first).

Constraint : you must plan the projects together.
Planning each project one at a time will not free resource availability : when a resource is planned on one project's task planning another project will not be able to move this first planning.


 
Posted : 22 Nov 2011 18H57
Evgueni Kolossov
(@ekolossov)
Posts: 566
Contributor
Topic starter
 

Ok, thank you very much


 
Posted : 22 Nov 2011 19H28