Resource availability

16 Posts
2 Users
0 Reactions
15 K Views
Evgueni Kolossov
(@ekolossov)
Posts: 566
Contributor
Topic starter
 
[#252]

Hi,
I have a question about setting up task: if i am setting task and assigning it to user without specifying the start date but with predecessor set and the duration specified and constraint as soon as possible I would expect this task will appear at the first available date for the assigned resiource but in Gantt chart I can see the link from predecessor to unknown time in past.
What I am doing wrong?
Another question: how to set up critical path?

Regards,
Evgueni


 
Posted : 24 Nov 2011 14H27
(@babynus)
Posts: 14952
Member Admin
 

You must replan the projet (calculation is not automatic).

Critical path is not managed in Project'Or RIA.
It is a identified evolution, not planned yet.


 
Posted : 24 Nov 2011 16H18
Evgueni Kolossov
(@ekolossov)
Posts: 566
Contributor
Topic starter
 

What you mean by replan the project?


 
Posted : 24 Nov 2011 16H21
(@babynus)
Posts: 14952
Member Admin
 

Recalculate : on Gantt planning view, click on button on left of the start date...


 
Posted : 24 Nov 2011 16H25
Evgueni Kolossov
(@ekolossov)
Posts: 566
Contributor
Topic starter
 

This have moved the predecessor start date to the beginning of the project not the date it have been scheduled


 
Posted : 24 Nov 2011 17H16
Evgueni Kolossov
(@ekolossov)
Posts: 566
Contributor
Topic starter
 

Ok, if I understand it right, I need to recalculate project FROM THE DATE OF PREDECESSOR start date. Am I right?

Regards,
Evgueni


 
Posted : 25 Nov 2011 12H14
(@babynus)
Posts: 14952
Member Admin
 

I don't realy understand what you mean.
Generally, planning is calculated from current date.
Sometimes you may need to calculate from last consolidated date (for instance from start of week if you know that real work imputation is not up to date).

Could you precise your request ?

NB : you can find some interesting information on how planning works in the online manual...


 
Posted : 25 Nov 2011 13H16
Evgueni Kolossov
(@ekolossov)
Posts: 566
Contributor
Topic starter
 

Thank you very much - I think I finally got it right


 
Posted : 25 Nov 2011 13H17
Evgueni Kolossov
(@ekolossov)
Posts: 566
Contributor
Topic starter
 

Hi,

After project recalculation there are some issues with arrows pointing into nowhere or to the middle of the task. Can you please suggest how to fix that?

Regards,
Evgueni


 
Posted : 01 Dec 2011 15H36
Evgueni Kolossov
(@ekolossov)
Posts: 566
Contributor
Topic starter
 

And some arrows just not connected with the tasks at all... So, tasks dependencies is not displayed proper after project recalculation


 
Posted : 01 Dec 2011 15H39
(@babynus)
Posts: 14952
Member Admin
 

Dependency display issues have been fixed in V1.9


 
Posted : 01 Dec 2011 19H35
Evgueni Kolossov
(@ekolossov)
Posts: 566
Contributor
Topic starter
 

Thanks - when it will be released?

Regards,
Evgueni


 
Posted : 01 Dec 2011 19H38
(@babynus)
Posts: 14952
Member Admin
 

In the coming days...
(possibly this week-end)


 
Posted : 01 Dec 2011 20H08
Evgueni Kolossov
(@ekolossov)
Posts: 566
Contributor
Topic starter
 

Great! Pease notify us!

regards,
Evgueni


 
Posted : 02 Dec 2011 10H48
(@babynus)
Posts: 14952
Member Admin
 

I will send a newsletter.

NB : you must register to the website (different from forum registration) to recieve the newsletter.


 
Posted : 03 Dec 2011 16H29
(@babynus)
Posts: 14952
Member Admin
 

V1.9 is deployed !


 
Posted : 10 Dec 2011 19H47