Resource availability

16 Posts
2 Utilisateurs
0 Reactions
15 {numéro}K Vu
Evgueni Kolossov
(@ekolossov)
Posts: 566
Contributor
Début du sujet
 
[#252]

Hi,
I have a question about setting up task: if i am setting task and assigning it to user without specifying the start date but with predecessor set and the duration specified and constraint as soon as possible I would expect this task will appear at the first available date for the assigned resiource but in Gantt chart I can see the link from predecessor to unknown time in past.
What I am doing wrong?
Another question: how to set up critical path?

Regards,
Evgueni


 
Posté : 24 Nov PM 14:1111
(@babynus)
Posts: 14952
Membre Admin
 

You must replan the projet (calculation is not automatic).

Critical path is not managed in Project'Or RIA.
It is a identified evolution, not planned yet.


 
Posté : 24 Nov PM 16:1111
Evgueni Kolossov
(@ekolossov)
Posts: 566
Contributor
Début du sujet
 

What you mean by replan the project?


 
Posté : 24 Nov PM 16:1111
(@babynus)
Posts: 14952
Membre Admin
 

Recalculate : on Gantt planning view, click on button on left of the start date...


 
Posté : 24 Nov PM 16:1111
Evgueni Kolossov
(@ekolossov)
Posts: 566
Contributor
Début du sujet
 

This have moved the predecessor start date to the beginning of the project not the date it have been scheduled


 
Posté : 24 Nov PM 17:1111
Evgueni Kolossov
(@ekolossov)
Posts: 566
Contributor
Début du sujet
 

Ok, if I understand it right, I need to recalculate project FROM THE DATE OF PREDECESSOR start date. Am I right?

Regards,
Evgueni


 
Posté : 25 Nov PM 12:1111
(@babynus)
Posts: 14952
Membre Admin
 

I don't realy understand what you mean.
Generally, planning is calculated from current date.
Sometimes you may need to calculate from last consolidated date (for instance from start of week if you know that real work imputation is not up to date).

Could you precise your request ?

NB : you can find some interesting information on how planning works in the online manual...


 
Posté : 25 Nov PM 13:1111
Evgueni Kolossov
(@ekolossov)
Posts: 566
Contributor
Début du sujet
 

Thank you very much - I think I finally got it right


 
Posté : 25 Nov PM 13:1111
Evgueni Kolossov
(@ekolossov)
Posts: 566
Contributor
Début du sujet
 

Hi,

After project recalculation there are some issues with arrows pointing into nowhere or to the middle of the task. Can you please suggest how to fix that?

Regards,
Evgueni


 
Posté : 1 Déc PM 15:1212
Evgueni Kolossov
(@ekolossov)
Posts: 566
Contributor
Début du sujet
 

And some arrows just not connected with the tasks at all... So, tasks dependencies is not displayed proper after project recalculation


 
Posté : 1 Déc PM 15:1212
(@babynus)
Posts: 14952
Membre Admin
 

Dependency display issues have been fixed in V1.9


 
Posté : 1 Déc PM 19:1212
Evgueni Kolossov
(@ekolossov)
Posts: 566
Contributor
Début du sujet
 

Thanks - when it will be released?

Regards,
Evgueni


 
Posté : 1 Déc PM 19:1212
(@babynus)
Posts: 14952
Membre Admin
 

In the coming days...
(possibly this week-end)


 
Posté : 1 Déc PM 20:1212
Evgueni Kolossov
(@ekolossov)
Posts: 566
Contributor
Début du sujet
 

Great! Pease notify us!

regards,
Evgueni


 
Posté : 2 Déc AM 10:1212
(@babynus)
Posts: 14952
Membre Admin
 

I will send a newsletter.

NB : you must register to the website (different from forum registration) to recieve the newsletter.


 
Posté : 3 Déc PM 16:1212