Hello,
I don't really understand how the resource planning is working.
I allocated projects, activities etc... to my users. But nothing appear on the resource planning section, I got an alert "no data to display" I ticked "show wbs, closed items, left work, project level". I need to have all the tasks allocated for each users.
Could you clear up my mind ?
Thank you a lot,
Sincerely,
Dem
Hi dem,
did you approach the manual (press F1)? There are a lot of pages with tag "Planning".
Regards,
Klaus
To have a planning, you need to have some left work on your activities and run planning calculation.
Also pay attention to acess tight : possibly you visibilility is rstricted.
Also try and change project selection (on top left project selector)