Planning - Project specific calendar.

2 Posts
2 Users
0 Reactions
3,194 Views
 mr
(@zeby)
Posts: 1
New Member
Topic starter
 
[#2175]

Hello,

this is what I try to do: use ProjeQtOr to manage multiple projects simultaneously.

I wish I could put my resources, every week, 2 days on a project and two days on another project.

I tried with 4.5.4 version, but I have not succeeded ...

So my question is this: is it possible to choose a calendar by project ?
So I can say that on Monday/Tuesday is always a holiday for a project and Wednesday/Thursday for another... With an automatic calculation of schedules.

thank you in advance for your answers and good evening ...


 
Posted : 26 Jan 2015 19H34
(@babynus)
Posts: 14952
Member Admin
 

So my question is this: is it possible to choose a calendar by project ?

No calendars are defined for resources.

But you can get result you wish :
- set affectation rate to 40% on both projects (40% is 2 days on a 5 days week)
- define priority of project working on Monday & Tuesday with priority number lower (higher priority as 1 is highest priority) than other project
Run planning calculation


 
Posted : 27 Jan 2015 13H47