Hi,
Is it possible to manage that a ressource work only 5H all Fridays (work contract agreement), but 7h30 the rest of the week (Projeqtor has been setup with 7hours a day in global parameters).
Thanks for your lights.
Posté : 10 Avr PM 19:044
hi,
The only way to refine work per day is to use screen " absence" (or " time sheet")
yes, this requires to repeat the operation every week filling each friday with the amount of planificated work.
Posté : 14 Avr PM 12:044