Hi,
Is it possible to manage that a ressource work only 5H all Fridays (work contract agreement), but 7h30 the rest of the week (Projeqtor has been setup with 7hours a day in global parameters).
Thanks for your lights.
Posté : 10/04/2020 7:10 pm
hi,
The only way to refine work per day is to use screen " absence" (or " time sheet")
yes, this requires to repeat the operation every week filling each friday with the amount of planificated work.
Posté : 14/04/2020 12:44 pm