Ressource capacity different per day

2 Posts
2 Utilisateurs
0 Reactions
1,450 Vu
 BILA
(@lsigroup)
Posts: 304
Honorable Member
Début du sujet
 
[#6627]

Hi,
Is it possible to manage that a ressource work only 5H all Fridays (work contract agreement), but 7h30 the rest of the week (Projeqtor has been setup with 7hours a day in global parameters).

Thanks for your lights.


 
Posté : 10/04/2020 7:10 pm
(@alain-fourastie)
Posts: 366
Membre Moderator
 

hi,
The only way to refine work per day is to use screen " absence" (or " time sheet")
yes, this requires to repeat the operation every week filling each friday with the amount of planificated work.


 
Posté : 14/04/2020 12:44 pm