Peut on avoir un récapitulatif des imputations pour une seule ressource
Please post in english
is it possible to have a sumary of all the activities of a ressource
for example :
ressource 1 : activity in charge = activity A and activity B
ressource 2 ==> activity A and activity C
i would want to have
for ressource A on may 23th = x hours on activity A and y hours on activity B
The must would be :
on may, 23th, ressource 1 has a time work of x+y and its normal time of work for a monday is z hours...
thank you for your answer
Have a look at :
Report "Planing by Resource/Project/Activity"
Agenda view
Resource Planning view