Hello
I wish you an happy new year 🙂
I migrated to ProjeQtOr v6.0.5, from a database version v5.4.5 (yes, a bit old...). There weare 46 errors / warnings.
My project seems good but satursdays and sundays are now work days : could you tell me how to get them simply back to days off as they were before the migration ?
In environmental parameters / diary, I have one diary called "default" where I had written the other days off (public holidays = "jours fériés"). I could do the same with satursdays and sundays, for the 2 years of my project but it's a bit boring 😉
Thank you for your help.
PS : thank for having added in the new version the report I suggested "work plan per month and per resource" (that is where I found my resources work all days of the month 😉 )
I migrated to ProjeQtOr v6.0.5, from a database version v5.4.5 (yes, a bit old...). There weare 46 errors / warnings.
Please post log file here.
My project seems good but satursdays and sundays are now work days : could you tell me how to get them simply back to days off as they were before the migration ?
This can be changed in Global Parameters.
Hello,
Thank you for the information on days off in Global Parameters.
I join the log.
Sincerely.
Hi,
It looks like you upgraded twice up to V5.5.2....
Nothing blocking, all should work fine.
Thank you for looking at the log. I don't know how I did that but it's possible 😉
I confirm all seems ok, once satursdays and sundays made days off again.