Hi,
V9.0.2
in an activity the left work value is incorrect,
Assigned work is : 409.75
Real work is : 368.25
Left work shoud be : 41.5 but the value is at 355.75
i've tried "scan for issue and fix issue" did not solved the issue.
Anything else i can do to fix this issue
for now i have manually changed the value but i really don't know if its a good thing to do
thanks for you help
regards
Hello,
have you changed the assigned work with a higher value?
the only solution to change this when it happens is to change the rest manually like you did.
Hello, i can't tell if someone change the assigned work, but thanks for your reply i will change manually the rest value if it happens again.
Regards