[SOLVED] Activities -- Incorrect Left Work

3 Posts
2 Users
0 Reactions
1,618 Views
(@karl-binet)
Posts: 129
Active Member
Topic starter
 
[#7360]

Hi, 
V9.0.2
in an activity the left work value is incorrect, 
Assigned work is : 409.75
Real work is : 368.25
Left work shoud be : 41.5 but the value is at 355.75

 

i've tried "scan for issue and fix issue" did not solved the issue.

Anything else i can do to fix this issue

for now i have manually changed the value but i really don't know if its a good thing to do

thanks for you help

regards


 
Posted : 02 Mar 2021 16H46
Flou
 Flou
(@flou)
Posts: 253
Active Member
 

Hello,

have you changed the assigned work with a higher value?
the only solution to change this when it happens is to change the rest manually like you did.


 
Posted : 03 Mar 2021 13H31
(@karl-binet)
Posts: 129
Active Member
Topic starter
 

Hello, i can't tell if someone change the assigned work, but thanks for your reply i will change manually the rest value if it happens again.

Regards


 
Posted : 03 Mar 2021 15H48