Hi,
After 7 days of work, all activities planned by projeqtor (hours affected to an activity for a day) are automatically validated as real work if the technician did not entered some real work.
How and where do i change this automatism ?
Thank you
Posté : 17 Déc AM 10:1212
HI
Global parameter / automation / generation of alerts
Posté : 17 Déc AM 11:1212
Début du sujet
I found it :
Global parameter / automation / automatic planning calcul /
At the end of the section : "Alimentation automatique du réel :" Non
Posté : 17 Déc AM 11:1212