[SOLVED] Dealing with planned dates

7 Posts
2 Users
0 Reactions
8,429 Views
(@quentinb)
Posts: 10
Active Member
Topic starter
 
[#4780]

Hello,

New user on ProjeQtor, I'm trying to find the best way to use it and I have an unsolved issu with automatic planned dates.

Here is my need:
- I log activities, mainly as a ToDo list. Some of them can be planned, but many cannot.
- All activities without date are always shown on the current day on the planning (I'm fine with it)
- If I run a planning calculation on my project, all those tasks will receive a start and end date, which is something I dont want.

So my question is: Is there any possibility to avoid the setting of planned dates on this kind of tasks ?
Maybe a specific status on those activities ? or a different type of "ToDo" object that is missed and which can be easily converted to an Activity once planned ?

Regards,
Quentin.


 
Posted : 16 Nov 2017 13H59
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

So my question is: Is there any possibility to avoid the setting of planned dates on this kind of tasks ?

Not, not for activities.
Use actions instead of activities, wich is exactly the object ot define todo lists.


 
Posted : 18 Nov 2017 17H40
(@quentinb)
Posts: 10
Active Member
Topic starter
 

Okay, but how do you deal with complex tasks (not recordable as a simple action) that can't start right now ?
For example, your task isn't properly qualified yet, but you need to record it in your system. If i run a planning calculation, the current day will be injected as a start and end date. I dont really understand this behavior.

Can you enlighten me a little more please?

Regards,
Quentin.


 
Posted : 21 Nov 2017 18H41
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

Several solutions :
- change planning mode to "must not start before validated start date"
- add sependency with prior task
- add fixed milestone and add dependency

But I'm afraid this is not issue with projeqtor usage, it is misunderstanding of project management.


 
Posted : 21 Nov 2017 20H45
(@quentinb)
Posts: 10
Active Member
Topic starter
 

Hello,

I'm not telling this is a problem with projeQtor. I'm working in a French telecom company and my business unit is currently using Excel to manage tasks on projects. I'm just trying to check if a tool like this software can match with their habits, otherwise, they won't switch to it. So, I have to "play" with some standards of project management :).

By the way, thanks for your answers.

And a little feedback, I think it could be more user friendly if we could directly create, from an Activity, a related object (i.e an Action with a link to the Activity already defined) instead of just linking an existing one.

Regards,
Quentin.


 
Posted : 22 Nov 2017 12H57
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

And a little feedback, I think it could be more user friendly if we could directly create, from an Activity, a related object (i.e an Action with a link to the Activity already defined) instead of just linking an existing one.

You can !!!:woohoo: :woohoo: :woohoo: :woohoo:

When adding link, click on magnifier ...
B) B)


 
Posted : 22 Nov 2017 16H24
(@quentinb)
Posts: 10
Active Member
Topic starter
 

Hoo nice ! I missed this part ! Another problem solved 🙂

And I finally figured out how to deal with end dates. I used to manage my Activities with validated dates or duration, instead of using the field "work" and ressources assignment.

Thanks for your advices !

Regards,
Quentin.


 
Posted : 22 Nov 2017 17H38