[SOLVED] Duration in planning mode

6 Posts
2 Users
0 Reactions
4,563 Views
(@dengine)
Posts: 10
Active Member
Topic starter
 
[#3140]

Hello!

I'm trying to plan my project. I have tasks, that contain 32 stages every. Some stages are longer than one day. But ProjeQtOr plans in other way. All stage (activity with type "task") have 1 day (as showed on printsreen). I want to see all plan. How have I change my plan in ProjeQtOr to see in ProjeQtOr activities durations what I want?

Can you help me?


 
Posted : 07 Mar 2016 18H38
(@guilhem)
Posts: 30
Active Member
 

You must set the project workload in field "work" instead of field "duration".


 
Posted : 07 Mar 2016 22H37
(@dengine)
Posts: 10
Active Member
Topic starter
 

You must set the project workload in field "work" instead of field "duration".

When? When do I plan?


 
Posted : 07 Mar 2016 22H42
(@dengine)
Posts: 10
Active Member
Topic starter
 

I tried. But ProjeQtOr recalculated and didn`t change planned duration. (see attached printscreen)


 
Posted : 07 Mar 2016 23H01
(@guilhem)
Posts: 30
Active Member
 

Sorry : in fact you must assign those 31 days to your developer :


 
Posted : 08 Mar 2016 0H04
(@dengine)
Posts: 10
Active Member
Topic starter
 

Thank You!


 
Posted : 08 Mar 2016 0H24