Hello!
I'm trying to plan my project. I have tasks, that contain 32 stages every. Some stages are longer than one day. But ProjeQtOr plans in other way. All stage (activity with type "task") have 1 day (as showed on printsreen). I want to see all plan. How have I change my plan in ProjeQtOr to see in ProjeQtOr activities durations what I want?
Can you help me?
You must set the project workload in field "work" instead of field "duration".
You must set the project workload in field "work" instead of field "duration".
When? When do I plan?
Thank You!