Hello
we need your help to calculate the earned value for our projects using projeqtoria :
according to my understanding the revised value is the new planned value , how to calculate the earned value and what is the relationship with work margin and validated work.
Do you have a plan for integrating it into reports and integrate Estimated cost and end at complation.
thanks and regads
revised value is the new planned value
Yes, Revised = Real + Left
how to calculate the earned value and what is the relationship with work margin and validated work.
It's not so easy (otherwise it would be done already).
Maybe it could involve "technical progress".
Do you have a plan for integrating it into reports and integrate Estimated cost and end at complation.
Yes, earned value is in the roadmap (ticket #314)
Thank you for your prompt reply ,
I m thinking that Earned value could be = total project validated value x technical progress it seems’ the most close to the definition of EV in project management concepts , I did calculations of EAC and SAC based on that and ithe results seems to be realistic and acceptable , is that correct ?
Is The ticket planned in the near future or it does not have a Fiix Ed end tile yet
HI,
Yes it is the best way to assess this value as accurately as possible.
No date is settled. To be clear, it could be by funding.
Regards.