[SOLVED] Earned value calculation

4 Posts
3 Users
0 Reactions
1,945 Views
(@nhedhili)
Posts: 79
Active Member
Topic starter
 
[#7523]

Hello 
we need your help to calculate the earned value for our projects using projeqtoria :
according to my understanding the revised value is the new planned value ,  how to calculate  the earned value and what is the relationship with work margin and validated work.
Do you have a plan for integrating it into reports and integrate Estimated cost and end at complation. 
thanks and regads  


 
Posted : 04 May 2021 23H43
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

revised value is the new planned value

Yes, Revised = Real + Left

how to calculate  the earned value and what is the relationship with work margin and validated work.

It's not so easy (otherwise it would be done already).
Maybe it could involve "technical progress".

Do you have a plan for integrating it into reports and integrate Estimated cost and end at complation. 

Yes, earned value is in the roadmap (ticket #314)


 
Posted : 05 May 2021 20H47
(@nhedhili)
Posts: 79
Active Member
Topic starter
 

Thank you for your prompt reply ,
I m thinking that Earned value could be = total project validated value x technical progress it seems’ the most close to the definition of EV in project management concepts , I did calculations of EAC and SAC based on that and ithe results seems to be realistic and acceptable , is that correct ?

Is The ticket planned in the near future or it does not have a Fiix Ed end tile yet


 
Posted : 05 May 2021 21H49
(@alain-fourastie)
Posts: 366
Active Member Moderator
 

HI,

Yes it is the best way to assess this value as accurately as possible.
No date is settled. To be clear, it could be by funding.

Regards.


 
Posted : 06 May 2021 11H22