[SOLVED] Fraction of days for Activity duration

9 Posts
2 Users
0 Reactions
3,878 Views
Martin Maille
(@marty)
Posts: 19
Active Member
Topic starter
 
[#8283]

Hello people.
We're just starting to use PorjeQtor for the first time and as a Newbee user, I have my first Newbee question. And I did try to find the answer in the forum before I asked.  
Here it goes:
I'm putting together a project and assigning tasks.
I get into trouble when I try to enter a fraction of day for duration (ex: 0.5d or 0.25d),  I get blocked and an exclamation point warning. (see attached screenshot)
Is there an obvious reason for this like a setting or other rule that I did not find in the manual?

Thanks for your help.  I will be back with more, I'm shure. 🙂
  
 
 


 
Posted : 02 Jun 2022 2H01
(@marylene)
Posts: 592
Contributor Admin
 

To plan for half a day, you can use the "Manual planning" or "regular between two dates for half a day" or "quarter of a day" planning modes.

But in any case, the planning will take into account the workload of the resource and not the duration.
The durations are in full days on the Gantt so even for 0.5 workload, 1 day will be indicated in the duration


 
Posted : 02 Jun 2022 11H37
Martin Maille
(@marty)
Posts: 19
Active Member
Topic starter
 

Thanks Arkhanje.
Can you suggest where I can find an explanation of Manual Planning or something that will help me understand the workflow concepts and options I have?  I'M searching the help files with no results.
I have also looked at many videos that don't cover an entire workflow. 
Thanks  
Martin


 
Posted : 02 Jun 2022 17H58
Martin Maille
(@marty)
Posts: 19
Active Member
Topic starter
 

Correct me if I'm wrong.
I realize that there is a difference between PROGRESS-Duration, and Ressource Assigned Work.
From what I understand,
Progress Duration is for planning the timescale of the project (Only in full days if entered directly) ,
Ressourced assigned work which is the actual planned work and cost of the work.(Can be fraction of days.)
Ex:
If I plan 1 day for an activity in the Progress duration field, The gantt chart will display 1 day,
Once you assign work to a resource like 0.5 day, the cost will be calculated using 0.5 day and not 1 day.
Thanks for your help.


 
Posted : 02 Jun 2022 23H00
(@marylene)
Posts: 592
Contributor Admin
 

I'M searching the help files with no results.

Press F1 from ProjeQtOr...
Or go to the online manual accessible from the website here

 


 
Posted : 03 Jun 2022 11H37
(@marylene)
Posts: 592
Contributor Admin
 

Correct me if I'm wrong.
I realize there is a difference between PROGRESS-Duration and Resource Assigned Work.

absolutely

If I forecast 1 day for an activity in the Duration field, the Gantt chart will show 1 day,

once again, yes absolutely

Once you assign work to a resource as 0.5 days, the cost will be calculated using 0.5 days and not 1 day.

and yes !


 
Posted : 03 Jun 2022 11H40
Martin Maille
(@marty)
Posts: 19
Active Member
Topic starter
 

I'M searching the help files with no results.

Thanks.  I have done this at lenght before asking questions.

Press F1 from ProjeQtOr...
Or go to the online manual accessible from the website here

 


 
Posted : 03 Jun 2022 16H39
Martin Maille
(@marty)
Posts: 19
Active Member
Topic starter
 

Thanks for the confirmation. It helps. I'm slowly getting an understandding of the system.


 
Posted : 03 Jun 2022 16H41
(@marylene)
Posts: 592
Contributor Admin
 

Thanks.  I have done this at lenght before asking questions.

indeed, we realize that it was not clearly said. Thanks to you, it's done for the next version! Thanks for your feedback.

 


 
Posted : 08 Jun 2022 12H44