Hi,
I have a question about the right management of fields for activities in 'multiple update' form.
As an admin, in multiple update form I can see all the fields available (especially priorité) But as a project Leader, 'priorité' field is not available,
I have check the defaults rights : no clue as project leader have default access to priority modification on an activity of his project. I have not seen any forms or screens to specify the rights on 'multiple update' screen.
How can I give access to multiple update on activity priorité to project leader ?
Thanks
"Change priority project", "Change priority others element" and "Multiple update" are rights that you must give to the desired profile from the "specific access" screen.
Thanks for your answer.
I confirm that the defautl value seems good :
multiple update : yes
Change priority : yes
Change priority others element : yes
in Fact, the default profile of our project leader are members (so they won't move around the projects on the root in planning mode ) and as such the list is calculed according to this profile and not the profile of the project.
The rights for multiple updates are calculated on the default profile because this feature allows several elements of several projects to be updated simultaneously. So we refer to the default profile.
The change of priorities and priorities of the elements remain calculated on the profile on the project.