Hello,
I have created a new calendar for my company,and wanted to make it as a default calendar for all the resources at once.As there are lot of resources in the company,i cant modify
each resource with newly created calendar.It will be a huge procedure and will waste a lot of time.
Please suggest any solution for doing the same.
Thanks,
Naveen
Hello,
Very easy !
go on the list of resource. then go to multiple update ( a button on list area) , select all the resources, select your calendar on the field requested , it is done ! wonderful isn't it?
Hey ,Thanks for the reply,but I am not able to get multiple update button.What is meant by list area.Can you share the image showing the same,that will be helpful.
RTFM
Hey Thanks ,Problem was with icons which I was not able to identify.
Thank you