Forum

[SOLVED] How to mak...
 
Notifications
Retirer tout

[SOLVED] How to make a standard calendar as default calendar for all resources at once

5 Posts
3 Utilisateurs
0 Reactions
1,937 Vu
(@navver1990)
Posts: 49
Estimable Member
Début du sujet
 
[#7798]

Hello,

I have created a new calendar for my company,and wanted to make it as a default calendar for all the resources at once.As there are lot of resources in the company,i cant modify
each resource with newly created calendar.It will be a huge procedure and will waste a lot of time.
Please suggest any solution for doing the same.

Thanks,
Naveen


 
Posté : 29/09/2021 2:59 pm
(@alain-fourastie)
Posts: 366
Membre Moderator
 

Hello,

Very easy !
go on the list of resource. then go to multiple update ( a button on list area) , select all the resources, select your calendar on the field requested , it is done ! wonderful isn't it?


 
Posté : 29/09/2021 4:32 pm
(@navver1990)
Posts: 49
Estimable Member
Début du sujet
 

Hey ,Thanks for the reply,but I am not able to get multiple update button.What is meant by list area.Can you share the image showing the same,that will be helpful.


 
Posté : 30/09/2021 8:37 am
(@babynus)
Posts: 14952
Membre Admin
 

RTFM


 
Posté : 03/10/2021 8:47 pm
(@navver1990)
Posts: 49
Estimable Member
Début du sujet
 

Hey Thanks ,Problem was with icons which I was not able to identify.
Thank you


 
Posté : 04/10/2021 9:08 am
Share:
Retour en haut