Hello
When a project was created and canceled due to whatever reason, the only way for users which I found was to cancel every single activity, etc. one by one and then the sub-projects and finally the project itself. Because otherwise it complained by changing the state that there are still open tasks.
Regards
Posted : 01 Sep 2021 12H30
You can cancel many activities in one step with "multiple update" mode.