Hello,
i'm kind of stuck with an activity :
This activity has with 0.25 of work left. The manager of this task wants to close it, so he want's to get rid of the 0.25 left.
When editing the assignation, i can't find how to erase this time left. If i click on the 0.25 left it replaces it by a full day (This is what i've done in the capture).
Thanks for your help.
You must go to the Timesheet and change left work to zero
thanks, it worked perfectly.