[SOLVED] Left work with manual planning in activity

3 Posts
2 Utilisateurs
0 Reactions
2,269 Vu
(@brunof782)
Posts: 45
Trusted Member
Début du sujet
 
[#7053]

Hello,

i'm kind of stuck with an activity :

This activity has with 0.25 of work left. The manager of this task wants to close it, so he want's to get rid of the 0.25 left.

When editing the assignation, i can't find how to erase this time left. If i click on the 0.25 left it replaces it by a full day (This is what i've done in the capture).

Thanks for your help.


 
Posté : 19/11/2020 1:33 pm
(@babynus)
Posts: 14952
Membre Admin
 

You must go to the Timesheet and change left work to zero


 
Posté : 20/11/2020 10:50 am
(@brunof782)
Posts: 45
Trusted Member
Début du sujet
 

thanks, it worked perfectly.


 