Hello,

Why does the expected in the "Timesheet validation" not correspond to the planned load in the "work plan per resource and per week" report?
How can we manage resources that are allocated only a few days on the project and in an irregular way?

Thank you for your answer.


 
Posté : 28 Juil PM 18:077
(@marylene)
Posts: 592
Membre Admin
 

Hello !

Don't forget that on this report you have the actual work (informed about the imputations) and the planned work.

I can't seem to reproduce. I have no anomaly on my side.
Which ProjeQtOr version are you on? Do you have a screenshot?

and

There are planning modes like "recurring", "regular between dates", and "manual planning" that can help you organize irregular work better.


 
Posté : 29 Juil AM 11:077
(@linaewen23)
Posts: 23
Active Member
Début du sujet
 

Hello !

Don't forget that on this report you have the actual work (informed about the imputations) and the planned work.

I can't seem to reproduce. I have no anomaly on my side.
Which ProjeQtOr version are you on? Do you have a screenshot?

and

There are scheduling modes like "recurring", "regular between dates", and "manual planning" that can help you organize irregular work better.


 
Posté : 29 Juil PM 13:077