[SOLVED] Priority on projects ,subprojects and activities

6 Posts
2 Utilisateurs
0 Reactions
4,379 Vu
Martin
(@el-wallos)
Posts: 220
Active Member
Début du sujet
 
[#2947]

Hi Babynus

You answered me about priority on projects and subprojects but I did some tests and I'm not sure how to interpret the result.

My results were: (Sub= sub project, act=activities)
- If priority is medium (500) on all (project, subproject and activities), the lower WBS is planned first
- Project A (300) , Sub (500) , Act (500) and Project B (500), SUb (500) Act (300), the activity of project B is planned first, so the priority on activities is more important than priority on Project.
- Project A (300) , Sub (500) , Act (500) and Project B (500), SUb (500) Act (400), the activity of project B is planned first, I don't understand why?

Is it necesary to replan to take in charge the update of the priority even if "automatic run plan" is enabled?

Could you explain me the relation about priority between project, subproject and activities? How the priority is taken to create the planning?

Thanks.


 
Posté : 21 Jan PM 12:011
(@babynus)
Posts: 14952
Membre Admin
 

Thing on priority as global like [Priority on project].[Priority on activity]

Project A (300) , Sub (500) , Act (500)

priority is 500.500

Project B (500), SUb (500) Act (300)

priority is 500.300
Activity on B is planned first !

Priority on top project is not taken into account, only priority on project of activity.


 
Posté : 22 Jan PM 21:011
Martin
(@el-wallos)
Posts: 220
Active Member
Début du sujet
 

Thanks Babynus, it takes sense...that's why I need to change the priority of the sub project (if exists). :woohoo:

Thanks a lot for sharing your knowledge.


 
Posté : 25 Jan PM 12:011
Martin
(@el-wallos)
Posts: 220
Active Member
Début du sujet
 

Is it necesary to replan to take in charge the update of the priority even if "automatic run plan" is enabled?

Could you confirm me ?


 
Posté : 25 Jan PM 19:011
(@babynus)
Posts: 14952
Membre Admin
 

Yes and no.
Automatic planning runs only on Gantt view.
If you change priority on Activity view, you have to run planning manually.
But if you do in on Gantt view, planning should be recalculated automatically.


 
Posté : 27 Jan PM 19:011
Martin
(@el-wallos)
Posts: 220
Active Member
Début du sujet
 

Thanks, I have a better understanding about how to use the priority on ProjeQtOr.


 
Posté : 29 Jan PM 15:011