I have a question on the "Realwork allocation".
When I add and save value in realwork allocation, there are no update in the last line "total". But it's working in your demo. I don't find the parameter.
And a "ticket" don't add time on "planning activity". The time is add on the "parent activity" (red in screenshot) of the "planning activity" (green in screenshot).

Thank you.


 
Posté : 03/10/2016 8:21 pm
(@babynus)
Posts: 14952
Membre Admin
 

When I add and save value in realwork allocation, there are no update in the last line "total". But it's working in your demo. I don't find the parameter.

You must be sure to be in V5.5.2 and clear the browser cache.

And a "ticket" don't add time on "planning activity". The time is add on the "parent activity" (red in screenshot) of the "planning activity" (green in screenshot).

Yes, it is designed this way. Only real work on ticket is summed up to the activity.
This is done to be able to enter extra work directly on the activity, and be able to reduce value without setting a mess in real work of tickets.


 
Posté : 04/10/2016 8:39 pm
(@bourle)
Posts: 26
Trusted Member
Début du sujet
 

Ok. thx. I'm in v5.5.1


 