[SOLVED] Warning Threshold

4 Posts
2 Utilisateurs
0 Reactions
1,444 Vu
(@chandrashekhar)
Posts: 275
Contributor
Début du sujet
 
[#8208]

Dear Expert,

As is showing alert message by Projeqtor, I tried with extending validated date , but message is yet showing ! & I can't find Warning Threshold date (where it is mentioned?). Please guide how to manage?
 


 
Posté : 13 Avr AM 09:044
(@babynus)
Posts: 14952
Membre Admin
 

Value is in "Indicators" or "indicators per project".
An alert that has been generated will show until you "close" it, even if value that triggered it came back to normal.


 
Posté : 13 Avr AM 11:044
(@chandrashekhar)
Posts: 275
Contributor
Début du sujet
 

I would like to know how the warning threshold "04/08/2022" is showing?!


 
Posté : 13 Avr AM 11:044
(@babynus)
Posts: 14952
Membre Admin
 

Warining value is calculated from indicator definition.
If you define indicator on Activity for Validated end date (your example) with warning value at 1 open day, warning value for the activiy is calculated as 1 open day before validated end date.
For instance if validated end date is 2022-04-12, warning value is 2022-04-11.
For instance if validated end date is 2022-04-11, warning value is 2022-04-08


 
Posté : 13 Avr PM 20:044