Value is in "Indicators" or "indicators per project".
An alert that has been generated will show until you "close" it, even if value that triggered it came back to normal.
I would like to know how the warning threshold "04/08/2022" is showing?!
Warining value is calculated from indicator definition.
If you define indicator on Activity for Validated end date (your example) with warning value at 1 open day, warning value for the activiy is calculated as 1 open day before validated end date.
For instance if validated end date is 2022-04-12, warning value is 2022-04-11.
For instance if validated end date is 2022-04-11, warning value is 2022-04-08