I'm using your software since 3 weeks but i don't understand the difference between each date when i create a project or an activity.
What is the difference betwen :
Valided
Planned
Real
Requested.
Thank you very much and have a good day 🙂
Requested = the first request from your customer (his Christmas wish list)
Validated = what you finaly committed with your customer. It is your baseline.
Planned = calculated by PrjeQtOr taking into account work assigned to resources, resources availability and all the constraints on tasks and resoures.
Real = defined from real work allocation (real start date = first date for real work)
Thank you very i understand now 🙂